Expand the Fuerabamba secondary electrical grid (central and upper sectors) to increase electricity supply.
The project included mounting of 20 concrete poles, provision of guy-wires, earthing, mounting, assembly of conductor cables, lighting systems, 34 electrical connections, and earthing and isolation electrical tests. The project has also helped some residents start small businesses.